Hidden damage, a new roof and two extra months of work later, the Uxbridge Road library is open again.

Howick Library reopened this week, more than eight months after it closed for repairs to a leaking building.

The library and the Fencible Lounge next door shut on 16 February for what was meant to be a seven-month job.

Once the walls and roof were opened up, builders found more damage than expected, and the reopening moved from August to November.

Howick Local Board chair Bruce Kendall said nobody could know the full extent until the building was stripped back.

“We knew with leaking buildings, you actually don’t know how bad it’s going to be until you open it up,” he said.

“It was a lot worse than we originally anticipated.”

“We’re all shocked at how expensive it was, but it’s a lot cheaper than a new building and faster too.”

“The Board was unanimous in spending the money and getting this library and this space back up to speed.”

The Board approved the renewal in January at an estimated cost of $2,639,747, including about $59,000 for a temporary library service.

The original scope was new cladding, membrane roofing, some air-conditioning units, refurbished ducting and repainting.

During the work, the timber and brick cladding also had to be replaced, and the Board chose to replace the whole metal roof rather than patch it.

Principal project manager Bill Jackson said the team used the closure to deal with other work while the building was open.

“While we’re doing a project like this, we also looked to see if there’s any ancillary areas that need to be addressed,” he said.

“It makes sense to do it while you’re there.”

“Things like solar and things like acoustics and just some of the finishes and some of the heavy wear rooms like the bathrooms.”

Jackson said the work also uncovered an out-of-date fire rating and air-conditioning ducts that had all rusted.

“The whole project has been risk-managed so that the costs don’t blow out, and it’s been independently assessed,” he said.

He said staff went back to the Board to reprioritise part of its work programme so money could be moved to the library.

“The other projects will be done, but they’ll be in later years,” he said.

New public toilets in Howick and improvements to the Lloyd Elsmore Park mountain bike trail are now scheduled for the 2028/2029 financial year.

While the library was shut, a temporary service ran from Howick War Memorial Hall in Picton Street from 23 February to 16 October.

“When we closed the library, had to consider whether we do a pop-up library, and we did,” Jackson said.

“It’s been really popular, and that was part of the budget.”

He said the result was worth the disruption.

“It’s going to be safe, it’s going to be dry, and it’s going to not have the interruptions of service that we might have had if we would have left it and not done this project,” he said.

Jackson said Howick would now have “pretty much a brand new awesome building that we shouldn’t have to touch again for many years”.